Rail Production
TL;DR
- Purpose: Aluminum guide rails for electromagnetic acceleration
- Material: Cryogenic aluminum (cooled to -180°C)
- Mass: ~70 t per Mass Driver* (hollow profile, 1 km track)
- Wear: Replacement every 3-6 months (100-140 t/year per Mass Driver)
*Extended tracks: 2 km (~140 t), 3 km (~210 t).
Overview
Mass Driver rails are aluminum guides along which the projectile (container with mirror) travels. The rails serve simultaneously as: - Guides for the projectile - Electrical conductors - Part of the electromagnetic circuit
Rail Design
| Parameter | Value |
|---|---|
| Material | 99.5% pure aluminum |
| Cross-section | 200x300 mm (hollow profile, 15 mm wall) |
| Segment length | 10 m |
| Segments per track | 100* (for 1 km track) |
| Rail pair (2 pcs) | ~70 t Al per Mass Driver* |
*Extended tracks: 2 km (200 segments, ~140 t), 3 km (300 segments, ~210 t).
Rail Profile
300 mm
+--------------+
| +----------+ | <- 15 mm wall
| | | |
| | NaK | | 200 mm (cooling cavity)
| | | |
| +----------+ |
+--------------+
Wall cross-section: 14,100 mm² (0.0141 m²)
For 2 rails x 1 km: 28.2 m³ Al -> ~76 t
Rail Manufacturing
Production Process
| Stage | Equipment | Output |
|---|---|---|
| Billet casting with core | CCM-Al with ceramic core | 100x100 mm billets with 50 mm channel |
| Rolling to profile | Rolling mill | 200x300 mm profile with channel |
| Cutting to segments | Plasma cutting | 10 m segments |
| Heat treatment | Induction furnace | Stress relief |
| Surface polishing | Grinding mill | Ra <1 um |
Note: The cooling channel is formed during casting using a ceramic core (MgO), which is then removed.
Details: Rolling Mill, Grinding
Cryogenic Cooling
Problem: Aluminum has 60% of copper’s conductivity at room temperature.
Solution: Cooling to -180°C increases aluminum conductivity by 6x.
| Material | Conductivity +20°C | Conductivity -180°C |
|---|---|---|
| Copper | 100% | 400% |
| Aluminum | 60% | 360% |
Conclusion: Cryogenic aluminum at -180°C has conductivity nearly equal to copper at room temperature.
Cooling System
| Parameter | Value |
|---|---|
| Coolant | NaK (sodium-potassium alloy) |
| Coolant temperature | -150°C |
| NaK flow rate | 100 L/min per track |
| Radiators | Directed into shadow (-180°C) |
| Pump power | 100 kW |
Rail Wear
Causes of Wear
| Cause | Contribution | Consequences |
|---|---|---|
| Electrical arcing | 40% | Surface erosion |
| Mechanical abrasion | 30% | Groove formation |
| Thermal cycling | 20% | Microcracks |
| Oxidation | 10% | Darkening, corrosion |
Aggravating factor: 1275g acceleration creates very high mechanical loads over a short time (0.4 sec).
Service Life
| Operating Mode | Launches | Service Life |
|---|---|---|
| Intensive (600/day) | ~50,000 | 3 months |
| Medium (300/day) | ~50,000 | 6 months |
| Light (100/day) | ~50,000 | 1.5 years |
Material Balance
Per 1 Mass Driver (new, 1 km track):
| Component | Al Mass | Production |
|---|---|---|
| Rails (2 pcs x 1 km) | ~70 t | 42 t/day -> 1.7 days |
Replacement (wear, 1 Mass Driver/year):
| Mode | Replacements/year | Al consumption/year |
|---|---|---|
| Intensive | 4 | 280 t |
| Medium | 2 | 140 t |
| Light | 0.7 | ~50 t |
At 1000 Mass Drivers (intensive mode): 280,000 t Al/year for rail replacement alone.
Quality Control
| Parameter | Test | Standard | Action on Deviation |
|---|---|---|---|
| Conductivity | 4-point resistance measurement | >95% IACS | Remelting |
| Flatness | Touch probe | +/-0.5 mm | Grinding |
| Microcracks | Visual (cameras) + load test | No visible defects | Rejection |
| Surface finish | Visual (cameras) | Ra <1 um | Polishing |
Rail Installation on Track
| Stage | Time | Robots |
|---|---|---|
| Trench preparation | 2 weeks | 10 Moles-M |
| Frame installation | 1 week | 20 Centaurs-M |
| Rail mounting (100 segments) | 1 week | 20 Centaurs-M |
| Joint welding | 3 days | 10 Centaurs-M |
| Cooling connection | 3 days | 10 Centaurs-M |
| Calibration | 1 day | Automation |
TOTAL: ~3-4 weeks from trench to ready rails. (Runs in parallel with frame and coil installation.)
See Also
- Rolling Mill — profile production
- Coil Winding — electromagnetic windings
- Tunnel Frame — support structure
- Track Assembly — Mass Driver installation