Mass Driver Track Assembly

TL;DR

  • Purpose: Final assembly of Mass Driver from ready-made components
  • Length: 1 km (base)*, 2-3 km for reduced g
  • Time: ~5-6 weeks for first MD (with pipelining), ~3-4 weeks for subsequent
  • Robots: Peak 50 robots (Moles, Centaurs, Crabs)

*For reduced loads: 2 km (637g) or 3 km (425g).


Overview

Track assembly is the final stage of Mass Driver production, when ready-made components (rails, coils, frame) are installed into a single 1 km structure.


Assembly Stages

Complete Sequence

Stage Time Robots Work
1. Site preparation 1 week 10 Centaur-M Leveling, marking
2. Trench excavation (1 km) 1 month 20 Mole-M Regolith excavation
3. Sulfur-concrete support installation 1 week 10 Centaur-M 100 supports every 10 m
4. Frame installation 2 weeks 20 Centaur-M ~85 truss sections
5. Rail laying 1 week 10 Centaur-M 100 segments of 10 m
6. Coil mounting 2 weeks 10 Centaur-M 1000 coils
7. Power cable routing 1 week 10 Centaur-M Coil power supply
8. Cooling connection 3 days 5 Centaur-M NaK circuit
9. Electronics installation 1 week 10 Centaur-M Sensors, controllers
10. Calibration and testing 3 days 5 Centaur-M Geometry, tests
TOTAL ~5-6 weeks* peak 50

*With parallel pipelining: stages 3-9 begin on completed trench sections while excavation continues ahead. Critical path ≈ trench duration + finishing work on last section.

With experience (subsequent MDs): ~3-4 weeks


Stage Details

1. Site Preparation

Work Description
Route selection Along the terminator (day/night boundary)
Geodetic marking Laser leveling, accuracy ±5 mm
Leveling Moles cut regolith mounds
Base preparation Installation of temporary structures

Route requirements: - Straight line (deviation <1 mm per 100 m) - Slope <0.1% (0.38g gravity is not critical) - Distance from craters >500 m (safety)


2. Trench Excavation

20 Mole-M robots dig a 1 km trench.

Parameter Value
Trench width 6 m
Depth 3 m
Excavation volume 18,000 m³ regolith
Mole productivity 100 t/day = ~35 m³/day
Time for 1 Mole ~514 days
Time for 20 Moles ~26 days ≈ 1 month

Details: Mole-M Robots


3. Sulfur-Concrete Support Installation

100 sulfur-concrete supports every 10 m to support the frame.

Parameter Value
Supports 100
Support mass 1 t sulfur-concrete
Foundation depth 2-3 m
Time per support 1 hour
TOTAL 100 hours = 1 week (10 robots)

Sulfur-concrete — construction material using sulfur (S) as binder and regolith as aggregate. Requires no water. Sulfur melts at 115°C, forming a strong structure upon solidification.


4. Frame Installation

Truss sections are placed on supports and welded.

Parameter Value
Frame sections ~85 (12 m each)
Section mass ~3 t
Installation time per section 2 hours (lifting + welding)
TOTAL ~170 hours = 2 weeks (20 robots)

Details: Tunnel Frame


5. Rail Laying

Aluminum rails are mounted on the frame.

Parameter Value
Rail segments 100 (10 m each, 2 rails)
Segment mass ~0.7 t
Laying time per segment 1 hour
Joint welding 10 min per joint
TOTAL ~130 hours = 1 week (10 robots)

Details: Rail Production


6. Coil Mounting

1000 coils are installed along the track.

Parameter Value
Coils 1000
Installation time per coil 15 min
TOTAL 250 hours = 2 weeks (10 robots)

Details: Coil Winding


7. Power Cable Routing

Power supply for coils from the energy system.

Parameter Value
Cable length ~3 km (main + branches)
Cross-section 100-200 mm² Al
Cable mass ~10 t
Routing time 1 week (10 robots)

8. Cooling Connection

NaK circuit for cryogenic cooling.

Parameter Value
NaK pipe length ~2 km
Diameter Ø20 mm
Radiators ~5,000 m² (directed into shadow)
Connection time 3 days (5 robots)

9. Electronics Installation

Sensors, controllers, control systems.

Parameter Value
Control units 34 (every 30 m)
Sensors 2,150 (current, temperature, position, vibration)
Cameras 20 (track monitoring)
Installation time 1 week (10 robots)

Details: Control Electronics


10. Calibration and Testing

Final check before launch.

Test Description
Track geometry Laser leveling, accuracy ±0.5 mm
Electrical circuits Ohmmeter, insulation, inductance
Cooling NaK circuit test, temperature -150°C
Test shot (empty) Empty container acceleration

Time: 3 days

Details: Testing


Material Balance

Per 1 MD (1 km):

Component Mass Source
Frame (steel) ~270 t Regolith Processing
Rails (aluminum) ~70 t Regolith Processing
Coils (aluminum) ~100 t Regolith Processing
Radiators (aluminum) ~50 t Regolith Processing
NaK coolant ~5 t Local
Electronics ~6 t Mostly Earth Import
TOTAL (MD) ~500 t ~99% local
Sulfur-concrete (supports) ~100 t Local (regolith + sulfur)
TOTAL installed ~600 t

With extension: 2 km (~875 t MD), 3 km (~1,300 t MD).


Construction Logistics

Transport Robots Role
Component delivery to site 10 Crab-M Material trailers
Heavy section installation 20 Centaur-M Cranes, manipulators
Welding and fastening 10 Centaur-M Welding robots
Cable routing 10 Centaur-M Cable pulling

See Also