flowchart TD
subgraph INPUT["MATERIALS"]
AL["Aluminum<br/>sheets, wire"]
FE["Iron<br/>profiles, wire"]
IMPORT["Imports<br/>electronics"]
end
subgraph FABRICATION["PARTS FABRICATION"]
WAAM["WAAM 3D printing<br/>housings, frames"]
GRIND["Abrasive grinding<br/>finish machining"]
CASTING["Casting<br/>rolling mill rolls"]
end
subgraph ASSEMBLY["EQUIPMENT ASSEMBLY"]
MNLZ_ASM["Caster assembly"]
MILL_ASM["Rolling mill assembly"]
ROBOT_ASM["WAAM cell assembly"]
end
subgraph OUTPUT["OUTPUT"]
EQUIPMENT["Equipment set<br/>for new factory"]
end
AL --> WAAM
FE --> WAAM
FE --> CASTING
IMPORT --> MNLZ_ASM
WAAM --> GRIND
GRIND --> MNLZ_ASM
GRIND --> MILL_ASM
GRIND --> ROBOT_ASM
CASTING --> MILL_ASM
MNLZ_ASM --> EQUIPMENT
MILL_ASM --> EQUIPMENT
ROBOT_ASM --> EQUIPMENT
style INPUT fill:#f0e68c
style FABRICATION fill:#fff3cd
style ASSEMBLY fill:#d4edda
style OUTPUT fill:#cce5ff
Factory Equipment Production
TL;DR
- Purpose: Manufacturing equipment for new factories
- Components: Continuous caster, rolling mill, WAAM cells, grinding cells, cranes, assembly jigs
- Technologies: WAAM 3D printing + abrasive grinding + assembly
- Time: ~4 weeks per equipment set for 1 factory
Overview
Each new factory requires an equipment set: casting machines (CCM), rolling mills, robotic cells. Equipment is produced at replicator factories (F-R) in the “Equipment Assembly” zone (200 m²).
Equipment Set for a New Factory
| Equipment | Mass | Material | Technology |
|---|---|---|---|
| Continuous caster (2 units) | ~10 t | Fe frame + local crystallizer | WAAM + casting |
| Rolling mill (6 stands) | ~15 t | Fe | WAAM + casting |
| Wire drawing mill | ~3 t | Fe + Si₃N₄ dies | WAAM + ceramics (local) |
| WAAM cells (3 units) | ~5 t | Fe + Al | WAAM + assembly |
| Grinding cells (2 units) | ~3 t | Fe + Al | WAAM + assembly |
| Overhead crane (1 t) | ~2 t | Fe + Al | WAAM + assembly |
| Assembly jig (10 positions) | ~5 t | Fe + Al | WAAM + welding |
| Roller conveyors | ~3 t | Fe + Al | Rolling + welding |
| TOTAL | ~46 t* |
*~51 t when packaged for transport (includes fixtures and crates).
Production Process
Key Equipment
Continuous Caster (MNLZ)
| Component | Mass | Material | Technology |
|---|---|---|---|
| Frame | ~4 t | Fe | WAAM + welding |
| Crystallizer (CCM-Al) | ~0.5 t | Fe-6%Mn steel + MgO coating | Casting + coating (local) |
| Crystallizer (CCM-Fe) | ~0.5 t | MgO ceramic | Sintering (local) |
| Pulling rolls (4 pairs) | ~2 t | Steel + ceramics | Casting + coating |
| NaK cooling system | ~1 t | Al tubes | Rolling + welding |
| Automation | ~0.3 t | Electronics | Import from Earth |
| Roller conveyor | ~1 t | Al | Rolling + welding |
Production time: 5-7 days (for 2 casters)
100% local crystallizer materials: Steel for Al (margin ~900°C), MgO ceramic for Fe (margin ~1300°C). No import required.
Details: Continuous Casting
Rolling Mill (6 stands)
| Component | Mass | Material | Technology |
|---|---|---|---|
| Frame (6 stands) | ~8 t | Fe | WAAM + welding |
| Rolls (12 pcs, 2 per stand) | ~5 t | Hardened steel | Casting + heat treatment |
| Drive motors (6 pcs) | ~1 t | Al windings | Assembly (local) |
| Inter-stand conveyors | ~1 t | Al | Rolling + welding |
Production time: 7-10 days
Critical parts: - Rolls — require hardening (heat treatment to HRC 55-60) - Al₂O₃ bearings — 100% local production (ceramic from regolith)
Details: Rolling Mill
WAAM Cells (3 units)
| Component | Mass per cell | Material | Technology |
|---|---|---|---|
| 6-axis robot arm | ~0.8 t | Al + Fe | WAAM + assembly |
| Welding torch | ~10 kg | Fe + Cu | Assembly + import |
| Rotary table | ~0.5 t | Fe + Al | WAAM + electronics |
| Control unit | ~50 kg | Al housing + boards | Housing local, boards import (~5 kg) |
Production time: 3-5 days for 3 cells
Critical import: Electronics boards only (~5 kg/unit). Housings — local WAAM production.
Details: WAAM 3D Printing
Grinding Cells (2 units)
| Component | Mass per cell | Material | Technology |
|---|---|---|---|
| 6-axis robot arm | ~0.8 t | Al + Fe | WAAM + assembly |
| Abrasive head | ~50 kg | Fe + Al₂O₃ | Local production |
| Rotary table | ~0.5 t | Fe + Al | WAAM + electronics |
| Control unit | ~50 kg | Al housing + boards | Housing local, boards import (~5 kg) |
Production time: 3-5 days for 2 cells
Advantages over CNC: - No imported high-speed spindle (saves ~0.4 t/factory) - Al₂O₃ abrasive (corundum) — 100% local production from regolith - Same Centaur-M robot as WAAM — standardization - Dry machining in vacuum (no coolant)
Machining accuracy: ±0.05 mm (sufficient for housings and frames)
Details: WAAM 3D Printing — post-processing
Overhead Crane (1 t)
| Component | Mass | Material | Technology |
|---|---|---|---|
| Main beam | ~1 t | Fe | WAAM + welding |
| Trolley | ~0.5 t | Fe + Al | Assembly |
| Hoist | ~0.3 t | Fe + Fe-Mn cable | Wire drawing + stranding (local) |
| Electric drive | ~0.2 t | Al windings | Assembly (local) |
Lifting capacity: 1 ton
Span: 30 m (dome width)
Production time: 3-5 days
Material Balance
Per 1 equipment set (~46 t):
| Material | Mass | Source |
|---|---|---|
| Iron (Fe) | ~30 t | Regolith processing |
| Aluminum (Al) | ~10 t | Regolith processing |
| Al₂O₃ (abrasive + bearings) | ~1 t | Regolith processing |
| Electronics boards | ~55 kg | Import from Earth |
Localization: ~99.9% by mass
Critical import: ~55 kg per factory (boards only, housings local)
Import breakdown: - MNLZ automation boards (2 units): ~30 kg - Control unit boards (5 units): ~25 kg
Savings vs CNC: Eliminating imported spindles = ~660 t savings across 1,645 factories
Production Timeline
| Week | Work |
|---|---|
| 1 | Fabricate caster parts (WAAM + grinding) |
| 2 | Assemble casters + fabricate rolling mill rolls |
| 3 | Assemble rolling mill + fabricate WAAM cells |
| 4 | Assemble grinding cells + overhead crane |
| TOTAL | ~4 weeks per set |
Parallelism: When producing equipment for multiple factories, processes run in parallel.
Equipment Testing
Before shipping to a new factory, equipment undergoes acceptance testing.
| Equipment | Test | Criterion |
|---|---|---|
| Caster | Trial casting (100 kg Al) | Ingot without cracks |
| Rolling mill | Rolling billet 100×100 → Ø20 mm | Profile within ±1 mm tolerance |
| WAAM cell | Print test part (100 mm cube) | Dimensions ±0.5 mm, porosity <2% |
| Grinding cell | Machine test part | Precision ±0.05 mm, surface finish |
| Overhead crane | Lift 1.5 t (150% load) | No deformation |
Testing time: 2-3 days
Transportation and Installation
After production, equipment is transported to the new factory.
| Stage | Time | Robots |
|---|---|---|
| Disassembly and packing | 1 day | 4 Centaurs-M |
| Transportation | 1 day | 6 Crabs-M |
| Installation inside dome | 2 days | 8 Centaurs-M |
| Power and automation connection | 1 day | 4 Centaurs-M |
| Commissioning | 1 day | Automation + 2 Centaurs-M |
| TOTAL | 6 days |
Production Energy Consumption
| Component | Power |
|---|---|
| WAAM cells (3 units) | 30 kW |
| Grinding cells (2 units) | 10 kW |
| Casting furnaces | 50 kW |
| Welding stations | 20 kW |
| Cranes and transport | 10 kW |
| TOTAL | ~120 kW |
Equipment Maintenance
After installation, equipment requires periodic maintenance.
| Operation | Frequency | Performer |
|---|---|---|
| Bearing lubrication | Weekly | Centaur-M |
| Machine calibration | Monthly | Automation |
| Rolling mill roll replacement | 1 month | Centaur-M (4 robots, 6 hours) |
| Wire drawing die replacement | 1 month | Centaur-M |
| Electronics repair | As needed | Centaur-M + spare parts import |
See Also
- Continuous Casting — main factory equipment
- Rolling Mill — semi-finished product manufacturing
- WAAM 3D Printing — parts fabrication technology
- Self-Replication — factory scaling
- Robot Production — Centaurs-M for assembly